Across 14 projects that reached bid, ACOT’s budget estimates landed within an average of 3.66% of the bid price. A look at the numbers behind that figure.

An estimate is only useful if it holds up when contractors price the work. One way to judge an estimator is to put the budget figure next to the bid that came back. ACOT keeps that record, and it is part of our capability statement.
Fourteen of the projects in ACOT’s cost estimating accuracy results went to bid. Across those fourteen:
The record spans a wide range of project sizes and types:
| Project | Budget cost | Bid price | % differential |
|---|---|---|---|
| Maximum Security Prison, RI | $56,000,000 | $54,800,000 | 2.14 |
| East Terminal Expansion “Pkg. B”, Lambert Airport | $46,632,000 | $45,500,000 | 2.43 |
| Student Center, University of Missouri | $22,156,000 | $21,300,000 | 3.86 |
| Benton/Stadler Hall Renovation Phase 2 | $18,200,000 | $17,900,000 | 1.65 |
| Elevator Upgrade, St. Louis Housing | $3,200,000 | $3,125,000 | 2.34 |
A $56 million prison and a $3.2 million elevator upgrade both landed within two and a half percent.
A budget that is too low leads to redesign, value engineering under pressure, or a funding gap at the worst possible moment. A budget that is too high ties up capital that could be working elsewhere. Estimates that track the market closely let an Owner make funding and scope decisions with confidence before the project goes out to bid.
Cost estimating sits alongside CPM scheduling and document control in ACOT’s program and construction management practice. The full table, including projects estimated at preconstruction, schematic and programming stages, is on our Experience page.
01 Keep reading
From constructability reviews to as-built drawings, a walk through the job site activities an ACOT construction management team takes on when it represents the Owner.
No general contractor, five or six bid packages, and one project manager whose allegiance is to the Owner. Here is how ACOT’s Owner’s Representative model is set up, and what it changes on a project.

“Rock Solid Service at the heart of your project”