Paddock Creek Improvements

Upon completion of a watershed study, approximately 220 feet of channel was lined with a concrete open box to carry the 100-year storm event.

01 Project summary

  • Construction Cost: $400,000
  • Project Fee: $45,000
  • Share of Work: 100%
  • Original Design Schedule: Five (5) months

Upon completion of a watershed study, approximately 220 feet of channel was lined with a concrete open box to carry the 100-year storm event. A transition was required at the north end of the project to meet an existing box culvert under Lindbergh Boulevard. AFRAM served as the prime consultant on this project, responsible for all civil design including drainage, hydraulics, and coordination with the District. Survey and geotechnical services were performed by subconsultants.

From the Stormwater & Sewer Experience Work Sheet in ACOT’s capability statement (AFRAM Corporation).